Series 90 Sectional Mast Systems
This mast was developed from Type 73 to meet the need to lift 100 kg antenna
loads up to 40 metres with great stability and safety. It uses a 4-legged
erection gear and guys at 90°. After erection all erection material
may be removed from the site. It is therefore possible to erect a number
of masts with a single set of erection equipment.
Rapidly knocked-down transportable sectional masts for Rear or Diplomatic communications in inaccessible places. This is a mast series which typically enables grid parabol antennas up to 3 metres diameter to be placed at heights up to 40 metres with the necessary torsional stability.
The 90 degree guy control system retains safety at all stages of erection and retraction. Built-in crane device enables heavy antennas to be mounted with minimum effort. Once erected, all erection gear may be removed leaving a semi-permanent mast. Capability : 10 to 40 metres, headload up to 300 kg. Erection example 30 metres : 5 Persons, time to erect with typical antenna, 2 ½ hours.
Brief Specification
- Tubular mast sections 150 mm dia x 2 metres long, aluminium alloy
- 1000 kg capacity lifting hoist
- Guy Controllers for each 10 metre of height
- Crane for mounting antennas
- Operating team is 2 persons for 10 metres, 5 persons for 40 metres
- Time to erect 20 metre mast with 100 kg load : 2 hours.
Standard Series 90 Field Mast Kits
| Cat No | Height | Number of Guying Levels | Max. Headload | Weight of Mast Kit |
| 10798 | 10 m | 1 | 300 kg | 115 kg |
| 10797 | 16 m | 2 | 280 kg | 180 kg |
| 10796 | 20 m | 2 | 250 kg | 205 kg |
| 10795 | 24 m | 3 | 230 kg | 255 kg |
| 10794 | 30 m | 3 | 200 kg | 320 kg |
| 10793 | 40 m | 4 | 100 kg | 385 kg |
| 10363 | Erection gear 1 required | 150 kg | ||
| 10362 | Guy Controller (per guy level) | 31 kg | ||